SRR / DCR
System Requirements Review / Design Criteria Review
Are the need, constraints, requirements, success criteria, and initial design problem sufficiently defined?
Authorizes
Begin structured concept development.
Required
New Programs or major scope changes.
Evidence reviewed
- Need and mission
- System boundary
- Requirements
- Constraints
- Success criteria
- Initial concept space
- Feasibility and risk
- Initial work structure
- Plan forward
CoDR
Conceptual Design Review
Has a preferred concept been selected from credible alternatives, with acceptable feasibility and risk?
Authorizes
Adopt the baseline concept and begin preliminary design.
Required
Where meaningful configuration alternatives exist.
Evidence reviewed
- Requirements and criteria
- Candidate concepts
- Trade studies
- Concept definition
- Feasibility
- Interfaces and budgets
- Risk and uncertainty
- Work decomposition
- Plan forward
PDR
Preliminary Design Review
Is the preliminary design complete enough to demonstrate that requirements can be met and interfaces can be controlled?
Authorizes
Begin detailed design and long-lead procurement as authorized.
Evidence reviewed
- Design baseline
- Requirements compliance
- Engineering analysis
- Interfaces
- Budgets and margins
- Risk and safety
- Verification and validation
- Manufacturability and implementation
- Work decomposition
- Plan forward
CDR
Critical Design Review
Is the detailed design complete, internally consistent, verifiable, and releasable for manufacture or implementation?
Authorizes
Release the design baseline for build or implementation.
Required
Before release of the integrated design baseline.
MRR
Manufacturing Readiness Review
Are the design, materials, tooling, procedures, work orders, personnel, and inspection controls ready to produce conforming hardware?
Authorizes
Begin controlled manufacturing or assembly.
Required
Before integration.
Are the test article, facility, instrumentation, procedure, hazards, personnel, and data system ready to execute the test safely and usefully?
Authorizes
Begin the approved test activity.
Required
Before an integrated test campaign.
FRR
Flight Readiness Review
Are the integrated vehicle or component, crew, site, procedures, weather limits, contingency plans, and open risks acceptable for flight?
Authorizes
Conduct the authorized flight operation.